2014 - 2016
Feasibility
Multiple routes were considered via Kenya and Tanzania. In April 2016, the Tanzanian Route was selected.
2014 - 2016
2017 - 2021
Pre-project
Route narrowing and finalization. Aerial and Land Environmental surveys including ESIAs and RAPs, FEED Engineering development and optimization, and Preparation for the tender process.
2017 - 2021
2022 - 2026
Project Execution
Land Acquisition. Contract Award for Detailed Engineering Procurement Construction and Commissioning, including First Oil oil first, Upstream facilities.
2022 - 2026
2026+
Operation
Oil transportation from Lake Albert Oilfields to the international markets.